Question 49 Quantitative Ability 2018 Medium MCQ +1.00 marks

A contractor agreeing to finish a work in 150 days employed 75 men, each working for 8 h daily. After 90 days only 2/7 of the work was completed. How many more men would be put on now, each working 10 h daily so as to finish the work in the stipulated time?